Leveling the structure is the most important phase of the installation. This must be done with the utmost accuracy and patience to be able to accept all the skins smoothly and not require additional work.
When leveling, one must first check that all posts and corner posts are plumb in all planes. To do so, one needs only to re-check each corner post and each post at the end of a partition at the exterior walls etc…
Once posts are confirmed to be plumb, the post where the gap between floor and ceiling is smallest will be chosen to begin the leveling process as follows.
From this point on you should level each and every post in the floor according to the same synchronized level of the laser.
Once all posts are leveled, IMT recommends spending the time to confirm them all before proceeding to the next stage.